Well, having gotten the building dried in and sealed up in December, I was able to take some time away from
the project to take care of some of life's other demands that had been piling up around here. So after around 5
months of setting closed up, I finally rolled the temporary electrical line back out to it, and started picking up
where I left off.
Because I will be doing a lot of wood working in this shop, I wanted a smooth sealed floor because trying to
keep fine sawdust swept up off from my existing garage's porous concrete floor has always been a pain.
So, knowing how things have a tendency to work out, I figured if I didn't do something about the bare concrete
now, I'd end up moving in benches and tools and then the floor would never end up getting done.
I opted to go with a concrete stain, and clear gloss solvent based sealer. I decided on a two toned (tan/brown)
spattered finish. The picture below shows the floor treatment I did, using a standard $20 pump up insecticide
type sprayer.
Needless to say, that with the three coats of clear gloss solvent based sealer (8 gallons total over 768 sq. ft.) I
got that smooth sealed (easy to sweep) surface I was after.
With the floor finished, I decided I wanted to get the ceiling up while there was still nothing in my way. Aside
from the elevator to the loft, I wanted simple access up and down from it. So, my next move was installing a pull
down staircase.
I mounted it between the trusses at the outside edge of the loft, so that at the top of the stairs you'd be
entering the loft from the side wall, and not taking up any of the loft's floor space with the staircase.
I had thought about buying one of these drywall jacks for several years. I finally did on my last project (an
addition on the house) I have to say that it is nice to have around when you need it. It certainly made installing
this pull down stair case a piece of cake to install.
With the legs cut off to size it's ready to climb.
Having only ran a few of the over head electric lines (enough to run the temporary lighting) before putting up the
ceiling, I had to make sure that all of the overhead wiring was completed first.
And now with all of the overhead rough in wiring complete the real fun begins.
The drywall jack is really earning it's keep because each sheet goes up, gets any outlet boxes marked, then
comes back down to be cut out, then goes back up to be screwed to the trusses.
Slowly sheet by sheet making my way across the ceiling. As I get to it, each light or overhead door track
support has to come down and then be re-installed after that sheet goes up.
Finally, 24 sheets, 480 screws, and a lot of handling, the ceiling is in. The only opening in it now is at the elevator shaft (pictured here against the back wall). But, the Ceiling and Floor are now complete.
Well thats all for this update. I hope it won't be long till the next one, now that I am back on the project again.