Welp, had my rough in electrical inspection and was failed on two things. One is that I put a subpanel in a large closet and he told me it can't be in a closet. At this stage, that is a lot of work to change given I've got piping running all around it in the wall. Also, failed me because apparently we need to have three wired smoke detectors in the addition all joined together so if one goes off, all go off. Just venting. Frustrating because I had him out last week and he didn't make mention of either when I told him I'd schedule my rough in.
Can someone enlighten me on the wired in detectors. I've never had to wire them in. Just used the battery ones in my house. How do I wired them to all go off if one does? Is it as simple as running them in sequence back to the breaker?
Can someone enlighten me on the wired in detectors. I've never had to wire them in. Just used the battery ones in my house. How do I wired them to all go off if one does? Is it as simple as running them in sequence back to the breaker?
You hacker, you!! 