Here are a few of the parts I've been making. Average order is for between 10-100K parts. Takes between 4-22 seconds to make each part. These parts are made from 6061. All parts here are made in less than 6 seconds each.
These are all made from 12L14. These take between 5-7 seconds to produce.
The part I'm holding in this pic is part of an explosion proof conduit system.
These are a mix of 12L14 and 4041 steels. The one that is up against the one I'm holding is the little ******* that takes 22 seconds to make. It's 4041 steel. The outer edge has a 2" radius cut into the OD. It runs VERY tight on the tolerance. I've I go .001" oversize the surface doesn't clean up. If I go .002" undersize it will fail QC. I have a tolerance of only .002" Yes I have to sharpen that form tool often. The rest of the parts here are in the sub seven second cycle time. The simple looking ring laying on it's side, under the blanking plugs, also is made from 4041 and has similar tolerances.
ALL of these parts are made on a single machine, the broached hexs, the teeth that are up-ended into the part everything. The part I'm holding is a sealing system for natural gas fittings.
Here is the machine They are made on.
Keith